The longest-running listed works are on the M11 northbound, where the hard shoulder between Junctions 9 and 9A is scheduled for structure maintenance for 182 days, until 30 April 2027. The expected delay is listed as slight, meaning less than 10 mins.
The duration is not a guide to how much a particular journey will be delayed. The Coggeshall Bypass closure is listed for 18 days but carries a severe delay estimate of more than 30 mins.
Which Essex roads have roadworks listed and when?
| Road and location | Work | Listed duration and end date | Expected delay |
|---|---|---|---|
| M11 northbound, Jct 9 to Jct 9A | Hard shoulder affected for structure maintenance | 182 days, until 30 April 2027 | Slight (less than 10 mins) |
| A12, both directions at Jct 29 | Carriageway closure for drainage works | 97 days, until 25 January 2027 | Slight (less than 10 mins) |
| A12, A120, A14 and M25; Copdock Roundabout to Jct 11 | Mobile lane and slip road closures, with diversion routes for horticulture work | 44 days, until 19 November 2026 | Slight (less than 10 mins) |
| A282 northbound, Dartford Crossing West Tunnel | Tunnel closure for maintenance, with a diversion | 25 days, until 28 November 2026 | Moderate (10 - 30 mins) |
| A120, both directions, Coggeshall Bypass between West Street and Colchester Road | Carriageway closure and diversion | 18 days, until 28 November 2026 | Severe (more than 30 mins) |
| A12 northbound, Jct 27 to Jct 28 | Carriageway reconstruction | 11 days, until 23 November 2026 | Moderate (10 - 30 mins) |
| M11 northbound, Jct 8 to Jct 9 | Hard shoulder works for barrier and fence safety repairs | 11 days, until 20 November 2026 | Slight (less than 10 mins) |
| A1089 northbound, Marshfoot to A13 westbound link road | Lane and link road closures for drainage, with a diversion | 7 days, until 24 November 2026 | Moderate (10 - 30 mins) |
Source: National Highways planned roadworks listings, covering works scheduled from 5 October 2026 to 30 April 2027.
Which roadworks could cause the biggest delays?
The expected delay ratings vary between schemes. The Coggeshall Bypass closure is listed as severe, or more than 30 mins, while the longer M11 hard shoulder works are rated slight, or less than 10 mins. These are expected delays, not a guarantee of what a driver will experience.
The A12 and A120 drainage works at Jct 29 are listed for 97 days, with a slight expected delay. The separate A12 reconstruction between Jct 27 and Jct 28 is listed for 11 days and a moderate delay.
How can I check for changes before travelling?
National Highways says plans can change. Check its live travel updates before setting off, particularly if your route uses the M11, A12, A120 or Dartford Crossing. Essex Highways also has local roadworks and travel information.
About the figures
National Highways published the listed schemes between 20 August 2025 and 12 November 2026. The scheduled works run from 5 October 2026 to 30 April 2027. Roadwork dates and arrangements can change, and the listed delay ratings are estimates.